We set up different sound liners in the "Insulation Material"SLSL - Decoiled StraightSL - Machine Cut StraightSL - FittingsAll the SL have the same Cost $/(sq Ft), but each has a different F time (min)/(Sq Ft)After a job is completely taken off (using the "generic" SL, we run a script that applies the correct SL to an item...This will then apply the correct SL to the item...Works like a charm...
Unless I have missed the point of this thread, why aren't you using value sets & assigning tables for the additional labour times for each value set?Each value set could then have it's own custom rule which references the insulation thickness & even if its double wall.