Author Topic: Co-ordinating Pipework  (Read 11172 times)

0 Members and 1 Guest are viewing this topic.

Offline docTopic starter

  • Senior Member
  • ****
  • Posts: 437
  • Country: us
  • Gender: Male
Co-ordinating Pipework
« on: Aug 01, 2011, 16:23:46 PM »
What is your opinion on which method of drawing is quicker...coordinating pipe as you draw or drawing pipe flat just to get it in then going through and coordinating?

Offline jmerch

  • Premier Member
  • *****
  • Posts: 2297
  • Country: us
  • Gender: Male
Co-ordinating Pipework
« Reply #1 on: Aug 01, 2011, 16:47:12 PM »
I like to discuss with the other disciplines and set your zones of where everyone will try to run, then get all the content in, then coordinate.  Me personally, I also try to route around where I think HVAC is going to go, etc. as I draw it in so I'm kinda avoiding conflicts as I go...but spending too much time and thought on this could backfire.

To start out the model, I try to get all the sloped piping in first and keep it high (if I can).  Then I let HVAC know that we pretty much can't move that and give them that model so they can somewhat route around as they're drawing.
Intel i7-6700K @ 4 GHz - 32GB RAM - NVidia Quadro M5000 - W10x64 - MEP & FABRICATION 2014/2017 - NAVIS 2017 - REVIT 2017.1

Offline mitchr_68

  • Full Member
  • ***
  • Posts: 202
  • Country: us
  • Gender: Male
Co-ordinating Pipework
« Reply #2 on: Aug 01, 2011, 17:14:02 PM »
I follow along same lines as jmerch. Get the gravity feed pipe in and fight a little with the duct guys. I also try to get my mains in on a rack to claim some space and coordinate with other trades as required.

Online audiocycle

  • Senior Member
  • ****
  • Posts: 457
  • Country: us
  • Gender: Male
Co-ordinating Pipework
« Reply #3 on: Aug 01, 2011, 17:15:04 PM »
Typical draw in 3D with order of precedence is as follows:
1) Plumbing Gravity Piping, Electrical racks of conduit & Lighting (Fire Protection for Upright systems)
2) Duct Mains & Branches
3) Pressure Piping (both HVAC & Plumbing)
4) Fire Protection & Miscellaneous Electrical Conduit
Barry Chupp
Autodesk Fabrication CADmep, Revit, Navisworks, Revizto, Stratus

Offline cadbyken

  • Premier Member
  • *****
  • Posts: 5345
  • Country: us
  • Gender: Male
Co-ordinating Pipework
« Reply #4 on: Aug 01, 2011, 17:16:30 PM »
Agree with all that have posted.  The zone idea is the best and then people can eaisly denote when they have to go out of their zone.
Ken Taylor - Atlantic Constructors, Inc
BIM Technology & Database Manager
Revit - not ready for Primetime given all of the add-ons, work arounds, and general issues with Fabrication in Revit.  Tired of them taking our money for little results.

Offline tnbndr

  • Premier Member
  • *****
  • Posts: 3117
  • Country: us
  • Gender: Male
    • J.F. Ahern
Co-ordinating Pipework
« Reply #5 on: Aug 01, 2011, 17:31:36 PM »
Quote
and keep it high (if I can).  

Lately I have found that if the sloped piping is running down a corridor it is better to keep it low. Other trades can go over the top to get into rooms on the sides of the corridor with higher ceilings.
But I am a duct guy, what do I know.
Fabrication 2013
AutoCad 2013x64(Plain Jane)
HP Elite Book 8740W, Processor i7 - 2.4GHz, 8 GB RAM
WIN 7(Enterprise) 64 Bit, NVIDIA Quadro FX2800M Video

Offline jmerch

  • Premier Member
  • *****
  • Posts: 2297
  • Country: us
  • Gender: Male
Co-ordinating Pipework
« Reply #6 on: Aug 01, 2011, 17:50:10 PM »
so far running it high has been the way to go to hit our inverts...gives us enough play too...then there's the "connect to existing" lines that are controlled by existing conditions.
Intel i7-6700K @ 4 GHz - 32GB RAM - NVidia Quadro M5000 - W10x64 - MEP & FABRICATION 2014/2017 - NAVIS 2017 - REVIT 2017.1

Offline docTopic starter

  • Senior Member
  • ****
  • Posts: 437
  • Country: us
  • Gender: Male
Co-ordinating Pipework
« Reply #7 on: Aug 01, 2011, 17:53:33 PM »
All good stuff to try/consider...thanks guys

Offline welchy78

  • Full Member
  • ***
  • Posts: 159
  • Country: us
  • Gender: Male
    • http://www.cjerickson.com
Co-ordinating Pipework
« Reply #8 on: Aug 01, 2011, 19:21:18 PM »
I agree with running the plumbing high. I always do my gravity pipe as high as possible; in coordination the other trades know that I'm as high as I can go and can only move it down.
Brian Welch
BIM Mgr - CJ Erickson Plumbing
Autodesk 2017 CAD/FAB/Navisworks/Revit
Boxx Intelfi Core i7-4790K 4.0Ghz, 32GB RAM, 4GB NVIDIA Quadro K3100M

Offline Zorg

  • Full Member
  • ***
  • Posts: 75
  • Country: au
  • Gender: Male
    • brief portfolio
Re: Co-ordinating Pipework
« Reply #9 on: Nov 13, 2013, 02:04:16 AM »
Always keep gravity dependant stuff as high as possible, it's an undisputable argument when other trades kick up a fuss. "It's shit.. it goes one way" if you want to avoid nasty clashes further into your model, modify the consultants routes as they will usually be the shortest (if they have thought about it at all). I suggest finding a wall to pin them to so you can maintain a sensible and linear route for your pipe and duct. The straighter your duct, pipe and containment, the less expensive it is to install/make and the less likely the site team will question your route intent. This will save you a few dozen phone calls during the lifetime of the site teams presence, I assure you  ;D

Remember, if you're pipework main run goes up and down more than once you need to re-think the run. It's also easier and cheaper to set a duct over or under the pipework. The pipe runs should have no more than 2 levels (per floor) above the datum unless the structure makes it other wise. This excludes plantrooms of course  :P A well coordinated pipework run will vent/drain only at the units, once at the main & the riser.
MEP Coordinator / Detailer

ACAD14 Vanilla
Navisworks Simulate 2014
Fabrication CADmep+ 2014

Offline lsm_drafter

  • Senior Member
  • ****
  • Posts: 465
  • Country: us
Re: Co-ordinating Pipework
« Reply #10 on: Nov 13, 2013, 16:52:38 PM »
It's also easier and cheaper for the plumber to set a duct over or under the pipework.

FTFY  ;)
You've got to eat them before they eat you!
CADmep 2017.0.0.F (26), AutoCAD 2017 x64
Windows 10 x64 on 256gb SSD, Corei7-7700K 4.2ghz 32gb RAM
8GB 256bit NVidia GeForce GTX1070, Dual 24" Monitors

Offline Tstright

  • Premier Member
  • *****
  • Posts: 1016
  • Country: us
  • Gender: Male
    • MEP Contractor
Re: Co-ordinating Pipework
« Reply #11 on: Nov 14, 2013, 17:59:23 PM »
Remember, if you're pipework main run goes up and down more than once you need to re-think the run.

Really?
"Only the Skilled Survive"

Offline cgb

  • Senior Member
  • ****
  • Posts: 377
  • Country: ca
  • Gender: Male
Re: Co-ordinating Pipework
« Reply #12 on: Nov 15, 2013, 14:10:37 PM »
Remember, if you're pipework main run goes up and down more than once you need to re-think the run.

Really?

The buildings I have been working on are so tight that site orders elbows by the gross.   If I went by this rule the pipe would all hang below the ceiling.


Offline cjehly

  • Premier Member
  • *****
  • Posts: 1257
  • Country: us
  • Gender: Male
Re: Co-ordinating Pipework
« Reply #13 on: Nov 15, 2013, 16:54:45 PM »
2 offsets huh?

someone doesn't jobs like the typical ones I get.
-Chris-

Offline Zorg

  • Full Member
  • ***
  • Posts: 75
  • Country: au
  • Gender: Male
    • brief portfolio
Re: Co-ordinating Pipework
« Reply #14 on: Nov 22, 2013, 05:29:45 AM »
Depends how much planning you put into it and what the base design looks like. If I'm doing general floor plans, 2 different levels of pipework is my maximum, not taking into considering the 1 or 2 odd offset for jumping over mains etc.

Plantrooms I always modularize and always have only 2 levels of pipework, more often than not under slung and top side mounted on channel or something.

MEP Coordinator / Detailer

ACAD14 Vanilla
Navisworks Simulate 2014
Fabrication CADmep+ 2014